Contract Signed for BTS Park Zielona Góra I – Construction Begins in Płoty

Contract Signed for BTS Park Zielona Góra I – Construction Begins in Płoty

12.01.2026
On January 12, 2026, a contract was signed for the comprehensive construction of a production, warehouse and service hall together with the infrastructure of the BTS Park Zielona Góra I logistics park. MBT Modern Building Team Sp. z o.o. was appointed as the general contractor for the investment. The project is being carried out by…

On January 12, 2026, a contract was signed for the comprehensive construction of a production, warehouse and service hall together with the infrastructure of the BTS Park Zielona Góra I logistics park. MBT Modern Building Team Sp. z o.o. was appointed as the general contractor for the investment.

The project is being carried out by BTS Development — a brand of the KOIMEX S.A. capital group. The investment is being built in the town of Płoty, in the immediate vicinity of Zielona Góra, providing convenient transport and logistics connections for future tenants.

Contract signing ceremony

BTS Development was represented by:

  • Janusz Kowalczyk – CEO

MBT Modern Building Team Sp. z o.o. was represented by:

  • Tomasz Kalisz – CEO
  • Karol Pinoczek – Commercial Proxy

Signing the contract marks the formal start of the project’s implementation phase.

Handover of the construction site and start of works

On January 14, 2026, the construction site was officially handed over and work on the project began.

BTS Development was represented by:

  • Jakub Zając – Project Engineer
  • Grzegorz Klecha – Construction Supervision Inspector

MBT Modern Building Team Sp. z o.o. was represented by:

  • Michał Walawender – Site Manager
  • Bartłomiej Potuczko – Project Manager

Also present at the event were:

  • Andrzej Zmyślony – Director of Construction Investments (BTS Development)
  • Joanna Grociak – Project Manager (BTS Development)
  • Piotr Cieślik – Works Manager (MBT Modern Building Team)

Investment implementation schedule

According to the adopted schedule, project implementation includes the following stages:

January 2026
Site handover and organisation

February–March 2026
Earthworks and foundation works

March–May 2026
Installation of the hall structure (precast elements, roof, walls)

April–June 2026
Roof and façade cladding and ensuring the building’s watertightness

May–June 2026
Installations, flooring and finishing works

July–August 2026
Final inspections and obtaining the occupancy permit

Another stage in the development of BTS Development

The start of works in Płoty marks another important step in the development of BTS Development and the consistent delivery of modern warehouse and production projects in western Poland.

BTS Park Zielona Góra I is an investment that responds to the growing needs of the logistics and production market, offering functional, modern space tailored to tenants’ requirements.

Other news

Trade Fairs
2026.04.16
BTS Development at the Poland & CEE Retail Summit 2026
halls, magazyny
2026.05.18
BTS Park Gorzów – a new development along the S3
2026.05.29
Rescue Drills at the BTS Park Świebodzin Construction Site