BTS Park Świebodzin

Start of construction: 2022.06
Construction finished: 2023.05
Świebodzin
Location
7 700 m2
Surface

The project is located in the southern part of Świebodzin, 3 km from the S3 and 12 km from the A2.

The project involves the construction of a hall with a total net area of 7 700 m2.
The floor area of the hall is 5 800 m2, with an office and staff area of 1 900 m2.

The net height of the hall is 9.40 m.

Location

Distance from:
Wrocław
220 km
Gdańsk
415 km
Szczecin
170 km
Warszawa
420 km
Wrocław
225 km
Berlin
180 km
S3
3 km
A2
10 km
Airport
30 km
Scroll

Technical specifications

Pole spacing 20.15 x 12.00 m
Net height 6.6 m (warehouse), 6 m (production)
Total area 7 700 m², production and warehouse hall 5 800 m², office 1 900 m²
Reinforced concrete construction
Natural lighting - skylights
LED lighting
Fire alarm system
Sprinkler system
Non-dusty industrial floor with a load capacity of 50 kN/m²
Gas heating
Destrifiers
Condensing reactive energy system
2 hydraulically adjustable docks
3 "ZERO" gates
Access control
CCTV monitoring
Air conditioning (office)
LAN installation (office)
Parking for cars and trucks
Natural green